Story · Rise and fall
Boeing 737 MAX: a shortcut that cost 346 lives
A rushed answer to Airbus, a hidden flight control system and two crashes

Racing Airbus
Since 2006 Boeing had been considering an all-new design to replace its 737. Then in December 2010 Airbus launched the A320neo, an updated jet with new engines and much better fuel economy, and in June 2011 it collected a record order backlog for a new airliner. In July American Airlines, a long-standing Boeing customer, ordered hundreds of Airbus jets. On 30 August 2011 Boeing's board responded: it approved the 737 MAX, a re-engined version of the old design, and dropped its new-aircraft project. Re-engining was expected to cost a fraction of a new programme. Orders flowed, and by January 2019 the MAX had more than 5,000 firm orders.
Sources: Boeing 737 MAX
Making a new plane fly like an old one
Boeing wanted the MAX certified as just another 737, which would spare airlines costly extra pilot training. But the bigger, more efficient engines sat higher and further forward and tended to push the nose up in some manoeuvres. Boeing's fix was software, the Maneuvering Characteristics Augmentation System, or MCAS, which pushed the nose down automatically so the plane handled like earlier 737s. Boeing persuaded the Federal Aviation Administration that MCAS could not fail catastrophically, and in 2016 the FAA approved removing references to it from the pilots' manual. Much certification work had been delegated to Boeing itself. The FAA certified the MAX in March 2017.
Sources: Boeing 737 MAX groundings · Boeing 737 MAX
Lion Air Flight 610
On 29 October 2018 a Lion Air MAX crashed into the Java Sea off Indonesia. Investigators found that a faulty angle-of-attack sensor had fed bad data to MCAS, which repeatedly pushed the nose down. A single sensor failure could trigger it. Boeing issued a bulletin on 6 November telling pilots to use an existing runaway trim procedure, and only named MCAS days later. Pilots had not known it existed. In December the FAA privately estimated that, unless MCAS was redesigned, it could cause 15 crashes over 30 years. Boeing said it would revise the software by April 2019, and the plane kept flying.
Sources: Boeing 737 MAX groundings
Ethiopian Airlines Flight 302
On 10 March 2019 an Ethiopian Airlines MAX crashed in Ethiopia. The two crashes together killed 346 people in less than five months. The pilots had followed the recommended procedure at first but could not recover. China and most other aviation authorities grounded the MAX within days, even as Boeing's chief executive, Dennis Muilenburg, publicly insisted the plane was safe. The FAA at first said it had no data to act on, then on 13 March cited similarities between the crashes and grounded it too. By 18 March all 387 MAX jets in service were on the ground, affecting 8,600 flights a week at 59 airlines.
Sources: Boeing 737 MAX groundings
Twenty months on the ground
Investigations by Congress, the FBI and other agencies examined how the plane had been certified. A House report in September 2020 found that Boeing had dismissed employee concerns about MCAS, put deadlines and budgets ahead of safety, and withheld key information from the FAA. Muilenburg was dismissed in December 2019 and replaced by the chairman, Dave Calhoun. Boeing halted MAX production from January to May 2020 and estimated a loss of 18.4 billion dollars for 2019. The FAA took back its delegated power to sign off individual MAX jets. With fixes required on every aircraft and improved pilot training, the plane was cleared in November 2020, after the longest grounding of a US airliner.
Sources: Boeing 737 MAX groundings
A fraud charge settled
In January 2021 Boeing settled a fraud charge over hiding information from safety regulators, agreeing to pay more than 2.5 billion dollars: a criminal penalty of 243.6 million, 1.77 billion in compensation to airlines, and a 500 million dollar fund for the families of the dead. The deal was a deferred prosecution agreement, under which charges would be dropped if Boeing met its terms. The only individual charged, a former chief technical pilot accused of misleading the FAA, was acquitted in March 2022. Altogether the crashes and grounding cost Boeing an estimated 20 billion dollars in fines, compensation and legal fees, and indirect losses of more than 60 billion from over 1,000 lost orders.
Sources: Boeing 737 MAX groundings
The door plug
On 5 January 2024 a panel plugging an unused emergency exit blew out of an Alaska Airlines MAX 9 in flight. Nobody died, but airlines then found loose bolts on other planes, and the FAA grounded 171 MAX 9s and audited Boeing's production. Prosecutors said Boeing may have breached its 2021 agreement. In July 2024 it agreed to plead guilty to a felony fraud charge and pay a 487.2 million dollar fine, but a federal judge rejected the deal, and in 2025 the Justice Department agreed a new arrangement under which Boeing avoided prosecution. Calhoun stepped down, and Boeing agreed to buy back its fuselage supplier Spirit AeroSystems for 4.7 billion dollars to bring 737 fuselage work in-house.
Sources: Boeing 737 MAX groundings · us-judge-approves-doj-decision-to-drop-boeing-criminal-case