Chernobyl and the nuclear business

A reactor built to meet the plan, and the industry it reshaped

Cover: Carlo Dani, CC BY-SA 4.0
  1. A reactor made for the plan

    The RBMK reactor was designed between 1964 and 1966, mainly at the Kurchatov Institute of Atomic Energy and the NIKIET design institute in Moscow. Soviet planners preferred it to the rival VVER, a pressurised water design like many in the West, largely because it was easy to manufacture. It needed no huge, thick-walled pressure vessel, so many more factories could make its parts, and its large output helped the government hit its economic targets. The RBMK-1000 design was fixed in 1968, when it was the world's largest reactor design. No prototype was built. It went straight into series production, starting at Leningrad, where the first unit opened in 1973.

    Sources: RBMK

    See this step on the map

  2. Building Chernobyl

    Work on the Chernobyl plant, near the new workers' town of Pripyat in Ukraine, began in 1972. It was meant to have twelve units, which would have made it the world's largest nuclear power station. Construction suffered from shortages of materials and workers, some inferior materials were used, and as the project fell behind schedule safety was neglected. Four RBMK-1000 reactors came online between 1977 and 1983, supplying about a tenth of Ukraine's electricity. Problems were known. A confidential NIKIET study concluded in 1980 that accidents were likely even in normal operation, but the response was to revise the manuals rather than fix the design.

    Sources: Chernobyl Nuclear Power Plant · RBMK

    See this step on the map

  3. 26 April 1986

    During a safety test on 26 April 1986, design flaws in reactor 4 led to an uncontrollable power surge, steam explosions and a fire that spread radioactive material across the Soviet Union and Europe. Two engineers died in the explosion and 28 more workers within three months from radiation sickness. About 49,000 people were evacuated at first, and some 68,000 more as the exclusion zone widened. The government admitted the accident only after raised radiation levels were detected in Sweden. The response involved more than 500,000 people and cost about 18 billion roubles, and total cost estimates run from 235 billion to 700 billion dollars.

    Sources: Chernobyl disaster

    See this step on the map

  4. The orders dry up

    The accident hit the nuclear industry well beyond the Soviet Union. Hundreds of reactor proposals around the world were eventually cancelled, among them Chernobyl's own units 5 and 6; unit 5 was about 70 per cent complete and was formally abandoned in 1989. New safety standards drove costs up, public opposition added legal and political expense, and the rate of new reactor construction fell sharply after 1986. The Netherlands and Finland postponed new plants, and Germany created a federal environment ministry with power over reactor safety. New international bodies followed, among them the World Association of Nuclear Operators, linking 130 operators in 30 countries so that engineers could inspect and learn from each other's plants.

    Sources: Chernobyl disaster · Chernobyl Nuclear Power Plant

    See this step on the map

  5. Italy votes, Enel retreats

    Italy felt the shock most directly. Its electricity industry had been nationalised in 1962 as Enel. After the 1973 oil crisis a 1975 energy plan called for more than 46 gigawatts of nuclear capacity by 1990, but by 1986 only one plant was under construction, at Montalto di Castro. After Chernobyl, Italians voted in a referendum in November 1987 to repeal several nuclear laws, including those allowing Enel to join international agreements to build and run nuclear plants. In 1988 the government decided to phase out nuclear power. Work stopped on the nearly finished Montalto di Castro reactors, which were later converted into a fossil-fuel power station, and the Enrico Fermi and Caorso plants closed early, in 1990.

    Sources: Nuclear power in Italy · Chernobyl disaster

    See this step on the map

  6. The price of joining Europe

    The RBMK's reputation followed it after the Soviet Union broke up. Lithuania's Ignalina plant ran two larger RBMK-1500 reactors without a robust containment building, and in Soviet times had produced 70 per cent of the republic's electricity. As a condition of joining the European Union, Lithuania agreed in 1999 to close it. Unit 1 shut at the end of 2004 and unit 2 at the end of 2009. The EU agreed to pay 820 million euros towards decommissioning and compensation, and international donors provided about 95 per cent of decommissioning funds. The government forecast a 30 per cent rise in household electricity prices, with fossil-fuel generation at Elektrėnai and imports filling the gap.

    Sources: Ignalina Nuclear Power Plant

    See this step on the map

  7. A 1.5 billion euro arch

    The concrete sarcophagus built in 1986 was never meant to last. In 1997 the G8 set up the Chernobyl Shelter Fund, managed by the European Bank for Reconstruction and Development, to pay for a permanent solution. Disputes over contractor selection and missing infrastructure caused years of delay, and only in September 2007 was the contract awarded to Novarka, a consortium of the French builders Vinci and Bouygues, with Bechtel managing the project for the client. Firms from 24 countries took part. The steel arch, 270 metres wide and more than 100 metres high, was assembled away from the reactor and slid over it in November 2016. It cost about 1.5 billion euros.

    Sources: Chernobyl New Safe Confinement · Chernobyl disaster

    See this step on the map

  8. Spent fuel and a drone

    The other three reactors kept running after the accident, and the last was shut down in December 2000, ending electricity production at the site. The American firm Holtec International built a dry storage facility in the exclusion zone for the plant's 21,297 spent fuel assemblies, to be held for 100 years; it was completed in 2020 and began taking fuel that November. Ownership of the new arch passed to Ukraine in July 2019. On 14 February 2025 a drone struck it, and in December the International Atomic Energy Agency reported that it had lost its main confinement function. Repairs were first estimated at 25 million dollars, but in spring 2026 the EBRD put the cost at about 500 million euros.

    Sources: Chernobyl Nuclear Power Plant · Chernobyl New Safe Confinement · 4066584-chernobyl-confinement-loses-key-safety-functions-comprehensive-restoration-needed-iaea.html · 74602

    See this step on the map